This source reports two treatments. Both are shown.
Protocol 1
DerivedN. C. Deno, 1998Difficulty Moderate
Start around June 19, 2027 for a May 3 last frost. Too late for spring 2027 — that needed starting on June 18, 2026.
Warm moist stratification
Duration: 90 daysTemperature: 70°F 21°C Light: dark
Cold moist stratification
Duration: 90 daysTemperature: 40°F 4°C
Warm moist stratification
Duration: 90 daysTemperature: 70°F 21°C Light: dark
about 9 months from start to sowing. Germination time not stated; 21 days assumed.
75% germination.
Protocol 2
DerivedN. C. Deno, 1998Difficulty High
Start around March 21, 2027 for a May 3 last frost. Too late for spring 2027 — that needed starting on March 20, 2026.
Cold moist stratification
Duration: 90 daysTemperature: 40°F 4°C
Warm moist stratification
Duration: 90 daysTemperature: 70°F 21°C Light: dark
Cold moist stratification
Duration: 90 daysTemperature: 40°F 4°C
Warm moist stratification
Duration: 90 daysTemperature: 70°F 21°C Light: dark
Cold moist stratification
Duration: 90 daysTemperature: 40°F 4°C
Warm moist stratification
Duration: 90 daysTemperature: 70°F 21°C Light: dark
1/8 germinated in this phase.
Steps after step 4 run on after germination.
about 12 months from start to sowing. Then 21 days to germinate.
62% germination in 7–21 days.